Angola: Total starts production from Zinia Phase 2, successful short-cycle development on Block 17

Total, operator of Block 17 in Angola, together with the Angolan National Oil, Gas and Biofuels Agency, has announced the start of production from the Zinia Phase 2 short-cycle project, connected to the existing Pazflor’s FPSO (Floating Production, Storage and Offloading unit). The project includes the drilling of nine wells and is expected to reach a production of 40,000 barrels of oil per day by mid-2022.
Located in water depths from 600 to 1,200 meters and about 150 kms from the Angolan coast, Zinia Phase 2 resources are estimated at 65 million barrels of oil.
The development of this project was carried out according to schedule and for a CAPEX more than 10% below budget, representing a saving of 150 million dollars. It involved more than 3 million manhours of work, of which 2 million were performed in Angola, without any incident.
Click on the link below for full report