Total Mozambique LNG project on schedule, work resumes this quarter

Total Mozambique LNG project on schedule, work resumes this quarter

Oil company Total on Wednesday said that the natural gas project in Mozambique remains on schedule and that construction work should restart this quarter after violence in the region suspended work.

“It is not because we have stopped for two or three months that we cannot reach the 2024 target,” the company’s chief executive Patrick Pouyanné said during the press conference to present the 2020 results.

The onshore works are suspended, but the engineering part is progressing rapidly and work off the coast continues, he added, in statements quoted by the Bloomberg financial information agency, in which he said that an agreement has been reached to ensure the safety of the area of the works in the northern part of the country.

Responsibility for security in the area falls to the government, Pouyanné said, adding that there was a plan to deploy forces in the region to control a perimeter of at least 25 kilometres, but that ideally, the entire province of Cabo Delgado should be secure.

Watch the press conference below:

Transcript Excerpts [via Nasdaq]:

“(…) So the second pillar of the strategy is LNG. LNG there, you know that it’s a strong fruit of our cash flow generation. By the way, 2020 demonstrated as well resilience. We have seen, of course, the Brent lost something like 30%. And we have lost itself 16%. Asian prices were at the bottom. And despite that, the cash flow generation from LNG US$3.2B was quite almost the same as last year. Why, in particular, because we continue to grow. We create value from scale and arbitrage 10% growth, US$38 [Phonetic] million tons of sales last year and we expect 10% more for 2021. So we benefited, of course, from the start in particular, which will deliver at full scale in 2021. And so that’s why we have this growth.

“But as you know, we have — this story is not over, because — and we did not stop it. Despite the crisis, we have the two flagship projects in Russia Arctic 2, which is 45% progress on Train 1 by end of 2020 and Mozambique LNG, which is all 21% progress on end 2020.

“We face clearly some security issues, you know it’s public and we are working with the Mozambique government. It does not have at this stage impact on the planning of the projects, which we’ll deliver by 2024, because we are still mainly in the engineering phase, the logistical phase and the offshore works have been maintained.

“But obviously the situation on the ground will need to be controlled and we have a clear plan securing an area of at least 25 kilometres around the project itself in order to be able to resume the work, which is our intent, with our contractors.

“But my highest priority is the security, not only of my staff, but fundamentally as the staff who work on the ground in Mozambique.

“In 2020, we have also maintained our commitment to LNG by sanctioning, like Helle said. The two only projects we have sanctioned worldwide, one is Train 7 in Nigeria and the other one, and we are happy to participate to that, is a project that Sempra is leading on the Pacific Coast of Mexico. It’s a very well located project, closer to Asia, Gulf Coast, obviously, you avoid the bottleneck of the Panama channel. And it’s low-cost project, because it’s fundamentally sort of regas plant, where we benefit from all the infrastructure, JTs are already — have already been invested. And it will be a sourced low-cost Permian gas.

“So that’s interesting. You can notice that on this slide systematically we put to you, we put an indication of the carbon intensity. And it’s linked to the climate ambition that we deliver. We said that we want the allocation of capital should be consistent.

“You don’t mind, probably, but let’s say that the historic LNG plants have a carbon intensity of around 40 kilo per CO2 per barrel or more, 40 to 50. So you can see that the last plants we are, unlike Mozambique, on which the Total teams have done some — to the plants which we inherited from Anadarko, we are making effort to minimize in order of projects [Technical Issues] we have made some interesting moves. (…)”